Foundiz offers a special sheet pile capping system. This innovative system developed  by Dawson Construction Plant (DCP) is fast, efficient and ensures safe working on heights and around water. The DCP Redeb Brackets and Soffit Panels can be assembled and re-used by almost anyone.  The capping system can be used for U- and Z-shaped sheet piles and also for combi walls.  The support brackets are light yet robust constructed and are designed to give many years of reliable service when well maintained and correctly used. The sheet pile capping system is available in three different classes.

Standard capping system

  • Support brackets with a working load of 1500 kg/bracket (Z-piles) and 2000 kg/bracket (U- piles)
  • Panel lengths from 2,5 up to 3,0 m1
  • Panel weights from 360 kg up to 477 kg
  • Maximum safe working load incl. panel from 1000 up to 1300 kg/m1
  • Options: location buttons, deep panel, Peri side panels

Medium capping system

  • Support brackets with a working load of 3000 kg/bracket
  • Panel length of 3,0 m1 
  • Panel weigth of 450 up to 477 kg  
  • Maximum safe working load incl. panel of 2000 kg/m1
  • Options: deep panel, Peri side panels

Heavy duty capping system

  • Support brackets with a working load of 15000 kg/bracket 
  • Panel length of 3,0 m1
  • Panel weight of 2000 kg
  • Maximum safe working load incl. panel of 10.000 kg/m1
  • Options: deep panel, Peri side panels

In case you might need a solution for a special application let us know and we can help. You benefit from more than 20 years of experience in the field of piling contracting and ground improvement.

Looking for temporary equipment? Please check out our rental fleet on this website or contact us.

×

Basket